Two Week Look Ahead
December 31, 2015
Over the past week, we have installed the KUB primary electrical duct bank across Cumberland, installed North side storm drainage to underground structure 15, and installed a new water line and new sewer line in North 20th Street.
As you travel on Cumberland, please be patient with traffic delays as our construction crews work to keep our project moving forward toward 19th and 18th Streets.
Over the next two weeks expect to see:
-
Sewer constrution in alley between North 19th and North 18th (behind Copper Cellar) - five week duration
-
A new water line in South 19th Street
-
Continuation of water and gas installation through 19th Street intersection
-
Continuation of Phase 2 Storm Drainage installation moving eastward toward 17th Street
-
Beginning of installation of south side temporary lighting