Two Week Look Ahead

February 4, 2016

 

During the past week gas services between North 20th and North 19th are geing tied over to the new main, all long side water service laterals and fire lines have been installed across Cumberland up to North 19th, sewer manholes 33B and 33C have been installed in the alley betweeen North 19th and North 18th, KUB primary electrial duct bank in North 18th is complete (pavement patching from the southa lley to the north alley will be completed by end of day 2/4/16), and the south side temporary lighting installation is underway and will be completed week of 2/8/2016.

 

Over the next two weeks expect to see:

 

 

  • Complete sewer construction in alley between North 19th and North 18th (behind Copper Cellar) - one week left in duration due to weather delays

  • Begin testing of new water system to North 19th

  • Begin install of water line "H" in North 19th

  • Continue Phase 2 storm drainage on the north side of Cumberland and in North 20th

  • Install 30" storm drainage piping in the alley between 18th and 19th

  • Complete south side temporary lighting (projected completion by Wednesday, 2/10/2016)