top of page

Two Week Look Ahead

January 28, 2016

 

As you travel on Cumberland, please be patient with traffic delays as our construction crews work to keep our project moving forward to 17th Street.

 

During the past week the new 8" gas line has been tested and in service up to North 19th Street. Irrigation service and 6" line to Long Branch Saloon has been installed, Sewer in the alley between North 19th and North 18th has been installed at the NW corner of Copper Cellar's property, KUB primary electrical duct bank in North 18th has progressed and the north side storm drainage has been installed to the corner of North 20th.

 

Over the next two weeks expect to see:

  • Continue sewer construction in alley between North 19th and North 18th (behind Copper Cellar), two weeks left due to weather.

  • Install long side irrigation at South 19th

  • Continue installation of primary electrical duct bank in North 18th

  • Asphalt patching of 18th where KUB duct bank was installed

  • Continue Phase 2 storm drainage on the north side of Cumberland and in North 20th

  • Install 30" storm drainage piping in the alley between 18th and 19th

  • Continue south side temporary lighting

bottom of page